Project Start Date: Sun 2/5/06
Project Finish Date: Tue 2/14/06

Task_Table1

ID
Task_Name
Start_DateFinish_DateLate_StartLate_FinishFree_SlackTotal_Slack
1
Requirement specification
Mon 2/6/06Thu 2/9/06Mon 2/6/06Tue 2/14/060 days0 days
2
Revised Use cases
Mon 2/6/06Mon 2/6/06Tue 2/7/06Tue 2/7/060 days1 day
3
Scenarios
Tue 2/7/06Thu 2/9/06Fri 2/10/06Tue 2/14/063 days3 days
4
Non-functional requirements
Mon 2/6/06Tue 2/7/06Mon 2/6/06Tue 2/7/060 days0 days
5
Estimates
Tue 2/7/06Tue 2/14/06Wed 2/8/06Tue 2/14/060 days0 days
6
Function point analysis
Wed 2/8/06Fri 2/10/06Wed 2/8/06Fri 2/10/060 days0 days
7
Problem decomposition
Tue 2/7/06Thu 2/9/06Wed 2/8/06Fri 2/10/061 day1 day
8
Reconcile estimates
Mon 2/13/06Tue 2/14/06Mon 2/13/06Tue 2/14/060 days0 days
9
Deployment diagram
Mon 2/6/06Tue 2/7/06Mon 2/13/06Tue 2/14/065 days5 days