Project Start Date: Sun 2/5/06
Project Finish Date: Tue 2/14/06
| ID | Task Name | Work | Duration | Start | Finish | % Work Complete |
|---|---|---|---|---|---|---|
| 1 | Requirement specification | 72 hrs | 5 days | Thu 2/9/06 | Mon 2/13/06 | 0% |
| 2 | Revised Use cases | 32 hrs | 2 days | Thu 2/9/06 | Fri 2/10/06 | 0% |
| 1 | Nachiket | 16 hrs | Thu 2/9/06 | Fri 2/10/06 | 0% | |
| 3 | Neeraj | 16 hrs | Thu 2/9/06 | Fri 2/10/06 | 0% | |
| 3 | Scenarios | 24 hrs | 1.5 days | Sun 2/12/06 | Mon 2/13/06 | 0% |
| 1 | Nachiket | 12 hrs | Sun 2/12/06 | Mon 2/13/06 | 0% | |
| 3 | Neeraj | 12 hrs | Sun 2/12/06 | Mon 2/13/06 | 0% | |
| 4 | Non-functional requirements | 16 hrs | 2 days | Thu 2/9/06 | Fri 2/10/06 | 0% |
| 2 | Bhavin | 16 hrs | Thu 2/9/06 | Fri 2/10/06 | 0% | |
| 5 | Estimates | 52 hrs | 3.5 days | Sat 2/11/06 | Tue 2/14/06 | 0% |
| 6 | Function point analysis | 24 hrs | 1.5 days | Sat 2/11/06 | Sun 2/12/06 | 0% |
| 1 | Nachiket | 12 hrs | Sat 2/11/06 | Sun 2/12/06 | 0% | |
| 3 | Neeraj | 12 hrs | Sat 2/11/06 | Sun 2/12/06 | 0% | |
| 7 | Problem decomposition | 16 hrs | 2 days | Sat 2/11/06 | Sun 2/12/06 | 0% |
| 4 | Max | 16 hrs | Sat 2/11/06 | Sun 2/12/06 | 0% | |
| 8 | Reconcile estimates | 12 hrs | 1.5 days | Mon 2/13/06 | Tue 2/14/06 | 0% |
| 4 | Max | 12 hrs | Mon 2/13/06 | Tue 2/14/06 | 0% | |
| 9 | Deployment diagram | 16 hrs | 2 days | Sat 2/11/06 | Sun 2/12/06 | 0% |
| 2 | Bhavin | 16 hrs | Sat 2/11/06 | Sun 2/12/06 | 0% |