Project Start Date: Sun 2/5/06
Project Finish Date: Tue 2/14/06

Tasks with Assignments

ID
Task Name
WorkDurationStartFinish% Work Complete
1
Requirement specification
72 hrs5 daysThu 2/9/06Mon 2/13/060%
2
Revised Use cases
32 hrs2 daysThu 2/9/06Fri 2/10/060%
1
Nachiket
16 hrs Thu 2/9/06Fri 2/10/060%
3
Neeraj
16 hrs Thu 2/9/06Fri 2/10/060%
3
Scenarios
24 hrs1.5 daysSun 2/12/06Mon 2/13/060%
1
Nachiket
12 hrs Sun 2/12/06Mon 2/13/060%
3
Neeraj
12 hrs Sun 2/12/06Mon 2/13/060%
4
Non-functional requirements
16 hrs2 daysThu 2/9/06Fri 2/10/060%
2
Bhavin
16 hrs Thu 2/9/06Fri 2/10/060%
5
Estimates
52 hrs3.5 daysSat 2/11/06Tue 2/14/060%
6
Function point analysis
24 hrs1.5 daysSat 2/11/06Sun 2/12/060%
1
Nachiket
12 hrs Sat 2/11/06Sun 2/12/060%
3
Neeraj
12 hrs Sat 2/11/06Sun 2/12/060%
7
Problem decomposition
16 hrs2 daysSat 2/11/06Sun 2/12/060%
4
Max
16 hrs Sat 2/11/06Sun 2/12/060%
8
Reconcile estimates
12 hrs1.5 daysMon 2/13/06Tue 2/14/060%
4
Max
12 hrs Mon 2/13/06Tue 2/14/060%
9
Deployment diagram
16 hrs2 daysSat 2/11/06Sun 2/12/060%
2
Bhavin
16 hrs Sat 2/11/06Sun 2/12/060%